The Truckee Sanitary District, founded in 1908, may be one of the oldest wastewater utilities in California, but it certainly isn’t antiquated. When the TSD Board of Directors voted to install a renewable energy system to meet the electricity needs at their administrative and operations facility on Joerger Drive, the district undoubtedly became one of the most forward thinking and innovative in the region.
The idea wasn’t a hard sell, according to General Manager Tom Selfridge. ‘One of our directors, Brian Smart, had experience with a solar system of his own, and during our pre-budget discussions a few years ago, the idea came up,’ Selfridge said. ‘Board member Mike Sullivan suggested a feasibility study, and everyone agreed.’ After an in-house study was done, the district hired a professional consulting firm, Enwood Energy, to help bring the concept to fruition. With plenty of available land, forward movement from the board, and no objections from the public, ‘we decided we could make it work, no matter what,’ Selfridge said.
TSD now boasts 535 ground-mounted photovoltaic solar panels using state-of-the-art microinverter technology developed by Enphase, a Petaluma-based company. While conventional solar panels feed into one central inverter before converting the collected direct current (DC) electricity into grid-compliant alternate current (AC) electricity, microinverter panels are each equipped with their own miniature electric inverters. ‘We elected to go with the microinverter technology because it’s easier to install and manage, more reliable, and produces between five to 25 percent more power,’ said Selfridge. ‘We’re very pleased with the performance so far.’
If all this techno babble makes your head spin, don’t despair. The system also offers something that makes it easy for even a novice to understand: a web-based interface available 24/7 that allows anyone to go online, view a page of icons that represent each individual panel, and track exactly how much electricity is being produced at any given time. District Engineer Blake Tresan likes this feature: ‘The system is easy to monitor, for us and our customers. It’s user friendly, and we always have real-time data.’
The 125-kilowatt system was installed by Premier Power, an El Dorado Hills company that has built hundreds of systems for commercial, government, and private customers across the country. (The company even has one particularly high-profile client, Jay Leno. His ‘Big Dog Garage’ solar system produces an estimated 78,697 kilowatt-hours annually.)
For TSD’s system, the strategy of using micro-inverters was a no-brainer. ‘The benefits of increased reliability while operating under harsh conditions, and the ability to manage the performance of each module, were key considerations in choosing the Enphase system,’ says Mark Santos, Premier Power’s senior renewable energy specialist. ‘The system was ideal for this installation, where altitude, temperature, snow, and transient debris present frequent challenges to system performance.’
As with all projects of this type and magnitude, cost was obviously an important concern. ‘A $20,000 rebate from the Truckee Donner Public Utility District’s Solar Initiative Program made the system more affordable and helped reduce the overall cost,’ Selfridge said, ‘and working with Kathy Neus and Steve Hollabaugh at the PUD was great.’
All told, it’s a million-dollar investment for the district, with an expected payback on the panels in 25 to 30 years. ‘The design intent was to meet 100 percent of the annual demand for electricity at our operations facility, which includes four buildings,’ Selfridge said. ‘Becoming a net generator is tricky, but we’ll be running power backwards in the summer and building our credit up.’
For now, the TSD’s renewable energy system offsets the electricity usage only from their headquarters on Joerger Drive, not from the sewer operations taking place within the 39-square-mile district itself. With 40 sewage lift stations across Placer and Nevada counties, 300 miles of gravity pipelines, nine miles of pressure pipeline, 3,927 manholes, and 36 full-time staff, that’s still a pipe dream, so to speak. But TSD has taken a giant step in the green direction and can certainly take credit for helping us all feel better when we flush.
Info: Visit the TSD solar tracking website to see system benefits and monitor power generation at: enlighten.enphaseenergy.com/public/systems/Nxhc1391.
~ Comment on this story below.