A biomass energy generation plant that was blocked from being built in Kings Beach is now being planned for Cabin Creek, and an environmental analysis of the project should be released for public review within days.

Following the public review of the environmental report, the project could be voted on by the Placer County Planning Commission as early as this fall.

The idea of building a biomass plant to generate electricity using forest slash from thinning operations has been a goal of Placer County’s for more than five years. The county settled on the Cabin Creek location between Truckee and Tahoe City last year after public opposition to building the energy plant in Kings Beach scuttled the North Tahoe location.

Advertisement

Brett Storey, Placer County’s biomass project manager, said the environmental impact report will be released to the public at the end of July for a 45-day review.

“The EIR has information that I think that people will be very pleased with,” said Storey of the air quality and greenhouse gas information in the report.

Storey said the county has worked hard to “make this site economically viable as well as environmentally viable.”

The biomass facility will use a process called gasification. Forest matter will be converted into fuel, which will power the electricity production. The wood will not be burned to power a steam turbine, as is common in older biomass facilities that use a process called “co-generation.”

“There will be no smoke that leaves our facility,” said Storey, while adding that some steam and other emissions will be generated by the 2-megawatt plant.

Placer County is working with private investors on the project. The county is planning on  partnering with a private company that would build the project, run the biomass facility, sell the energy, and seek carbon credits and green energy credits to pay for the plant.

The plant is planned as an 11,000-square-foot, two-story structure that would have an adjoining one-acre storage area for the forest material that would be used in the biomass plant. As opposed to earlier comments the county had made in news articles explaining why they chose the Kings Beach location as the preferred site, no new roads or transmission lines are needed at the Cabin Creek site.

Storey said he has been speaking with community groups, neighbors, and the Town of Truckee regarding the project.

Read the Environmental Impact Report (when it is released) at: http://www.placer.ca.gov/Departments/CommunityDevelopment/EnvCoordSvcs/E…