Alpine Meadows could see its first major residential development since the early 1980s if the proposed Alpine Sierra Subdivision is approved. The project, which is located at the top of the valley near the ski resort, proposes 47 units — a combination of single family homes, duplexes, and cabins — over 45 acres. Some residents, however, are concerned about construction impacts, especially if the Bear Creek Association grants access to the development through its private road.
The Alpine Sierra Subdivision is a project of Chris Nelson, a principal at Capstone Partners, LLC, in Portland, Ore., along with his wife and two other couples. The group purchased the Alpine Meadows property in 1997 when Nelson was living in Reno and owned a home in Bear Creek, a private subdivision in Alpine Meadows. The project comprises two components: a high density section composed of 14 townhomes and six custom cabins near the ski area and Stanford Alpine Chalet, and a low density area further east that includes 27 large lot estates above the Bear Creek subdivision.
The project’s major issue is access. The Alpine Sierra Subdivision proposes a single point of access off of Alpine Meadows Road near the ski resort, which would require building a bridge over Bear Creek (not to be confused with the subdivision of the same name). An internal road, around 1,500 feet long, would also have to be built to connect the project’s two sections. However, the developer and Placer County are also looking at a “co-equal alternative,” meaning it will get the same level of analysis in the environmental impact report, for a secondary access point. This access point off John Scott Trail is on a private road maintained by the Bear Creek Association and requires BCA board approval. If the board votes to allow access through its property, Alpine Sierra’s 27 homes would join the BCA and the internal road would no longer be built. According to developer Nelson, nixing the connecting road would eliminate one of the project’s biggest impacts and create more open space. Currently, the development includes 14.5 acres of open space.
“We are trying to come up with an alternative plan that would have a higher degree of acceptance,” Nelson said. “We are making a good-faith effort to develop plans that most homeowners support.”
However, some residents whose homes border the easterly portion of the project are concerned about the consequences of building a secondary access point through Bear Creek.
“This would mean a lot of construction traffic through John Scott Trail. There is big opposition,” said Michael Wilson, who has lived in Alpine for 12 years. “This is a small, dog-walking neighborhood. The construction equipment would be devastating to property values … It is such a huge project for a small neighborhood.”
Wilson also worries about the time it will take to build the project’s infrastructure, such as a sewer system and roads.
“There will forever be construction going on in Alpine Meadows,” he said. “Building the infrastructure will take years. It’s not like building a road out in Nebraska; you are blasting rock.”
Other Alpine residents who live further away from the development are more supportive of the project. Ken Gracey, who lives in Alpine and also owns land not far from Nelson’s development, applauds the project’s clustering of units near the Alpine Meadows ski area.
“We need it here for the long-term,” Gracey said. “The best thing is to put visitors by the base of the ski area rather than spreading them out over the valley.”
The project’s density is only half of that allowed by the Alpine Meadows General Plan. Written in 1968, it is the oldest general plan in Tahoe “if not the oldest in Placer County,” said Steve Kastan, field representative for Placer County Supervisor Jennifer Montgomery. “It’s more like a sales brochure.”
In addition to the internal road, both Nelson and Placer County senior planner Alex Fisch say the project’s biggest impacts are scenic ones that would affect hikers of the popular Five Lakes trail, located across the valley from the proposed subdivision.
The BCA will vote on the secondary access point by the end of May.
“Bear Creek is either a show stopper [for the second access road] or it allows access and the developers pay for it,” Gracey said.