Public Utility District to Replace Sewer for Restoration Project

    0

    Editor’s note, April 2: Corrected date.

    MEEKS BAY

    In a sewer and water committee meeting, Tahoe City Public Utility District (TCPUD) approved a bid for Lefrancois Engineering to relocate its state Route-89 Meeks Creek Bridge sewer line.

    TCPUD discovered the Meeks Bay segment of sewer line to be in conflict with Caltrans Meeks Creek Bridge Replacement Project under a U.S. Forest Service restoration project.

    The Forest Service project covers around 74 acres of National Forest land from Meeks Bay Resort up Meeks Creek. In replacing the bridge, TCPUD’s sewer line will be exposed. It will collaborate with Caltrans, expediting the project’s completion to fall 2027. 

    TCPUD will construct approximately 340 feet of new sewer main, along with replacing a manhole, creating a new manhole, and rehabilitating 480 feet of an existing, inactive sewer main.

    The Meeks Creek Bridge Replacement Project design is scheduled to be completed in May 2026 and construction will begin May 2027 after the completion of TCPUD’s sewer main. 

    “The purpose of this project is to address the existing fish passage barrier, improve wildlife connectivity, reduce the risk of upstream channel clogging, repair scour within the right of way downstream of the bridge, and enhance safety,” Caltrans says in its online purpose statement for the project.

    ~ MR